How does a 2 on 2 off schedule work?

By Al Davies ยท Updated November 11, 2026

Short answer: A 2 on 2 off schedule has a worker on for two days, then off for two days, and the cycle repeats every 4 days. Two crews, one the mirror of the other, cover every day.

What does the 4 day cycle look like?

Day of cycle1234
Crew AOnOnOffOff
Crew BOffOffOnOn

Because 4 does not divide into 7, a crew starts its two days on a different weekday every cycle. With a Monday start, Crew A works Monday and Tuesday in the first cycle, then Friday and Saturday in the second.

How many shifts fall in each calendar week?

Week (Mon to Sun)ShiftsWith 8 hour shiftsWith 12 hour shifts
Week 143248
Week 243248
Week 332436
Week 432436

This is Crew A over 28 days if it starts on a Monday. The pattern returns to the same weekdays after four weeks.

2 on 2 off work schedule: 28 day grid with dates

A 2 on 2 off work schedule is easiest to post as a 28 day grid with a date in every box. Copy the one below, keep Crew A and Crew B on separate rows, and change the start date to your own Monday.

28 day grid, sample start Monday Dec 7, 2026 (number = date)

WeekCrewMonTueWedThuFriSatSunShifts
Week of Dec 7Crew A7 ON8 ON9 off10 off11 ON12 ON13 off4
Crew B7 off8 off9 ON10 ON11 off12 off13 ON3
Week of Dec 14Crew A14 off15 ON16 ON17 off18 off19 ON20 ON4
Crew B14 ON15 off16 off17 ON18 ON19 off20 off3
Week of Dec 21Crew A21 off22 off23 ON24 ON25 off26 off27 ON3
Crew B21 ON22 ON23 off24 off25 ON26 ON27 off4
Week of Dec 28Crew A28 ON29 off30 off31 ON1 ON2 off3 off3
Crew B28 off29 ON30 ON31 off1 off2 ON3 ON4

How to read it: Crew A works the two days marked ON, then is off two days, and Crew B is on whenever Crew A is off. Every date has exactly one crew on, so the post is covered all 28 days. Crew A's four weeks come to 14 shifts, and Crew B's come to 14 as well. The cycle starts over on Monday Jan 4.

Blank grid for your own dates

Start date (Monday): ________ Shift hours: ________
Week of ____ Crew A: __ __ __ __ __ __ __ Crew B: __ __ __ __ __ __ __
Week of ____ Crew A: __ __ __ __ __ __ __ Crew B: __ __ __ __ __ __ __
Week of ____ Crew A: __ __ __ __ __ __ __ Crew B: __ __ __ __ __ __ __
Week of ____ Crew A: __ __ __ __ __ __ __ Crew B: __ __ __ __ __ __ __
Mark ON or off, then count shifts per week in the last column.

To build your own, write ON in the first two boxes for Crew A, off in the next two, and repeat across the rows without restarting at each Monday. Crew B is the mirror.

Where does overtime show up?

Over those 4 weeks, 12 hour shifts add up to 168 hours, or 42 a week on average. The Department of Labor treats each workweek as its own set of seven 24 hour days, and it does not let an employer average hours over two or more weeks. So weeks 1 and 2 each carry 8 overtime hours, and weeks 3 and 4 carry none.

Shifts of 8 hours stay under 40 in every week of the cycle.

What do workers get from it?

Short runs. No one works more than two days in a row, and every worker has a break after each pair. The cost is that it is rarely a clean weekend off, since weekends land at random.

How do you post it?

Give each crew a row and mark week starts so people can find their weekends. Print the week by role with your events and a QR code. Printing also posts it to your team. For longer blocks instead, see the 4 on 4 off schedule. For building the week from nothing, use our employee schedule guide.

Your state may add its own overtime rule. This page is general information only, so call your state labor office.

FAQ

How many crews do I need?

Two, one the mirror of the other, to cover seven days.

Does a worker ever get a weekend off?

Sometimes. Weekends fall at random because the cycle is 4 days.

Do 8 hour shifts reach overtime?

Not in this cycle. The most a week gets is 32 hours.

Can the 4 week average avoid overtime?

No. The Department of Labor says hours are not averaged across weeks.

What does a 2 on 2 off work schedule look like on a calendar?

Each crew works two days, is off two, and repeats, so the on days drift across the weekdays. The sample grid above shows 28 days with dates for Crew A and Crew B.