What is a 4 on 2 off schedule?
By Al Davies ยท Updated November 11, 2026
Short answer: A 4 on 2 off schedule means four working days followed by two days off, repeating every 6 days. Because 6 days do not match a 7 day week, a person averages about 4.7 shifts a week. Three crews staggered by two days keep two posts staffed every day.
How do three crews fit together?
| Day | Crew A | Crew B | Crew C |
|---|---|---|---|
| Day 1 | On | Off | On |
| Day 2 | On | Off | On |
| Day 3 | On | On | Off |
| Day 4 | On | On | Off |
| Day 5 | Off | On | On |
| Day 6 | Off | On | On |
Crew A works days 1 to 4. Crew B starts two days later and works days 3 to 6. Crew C starts two days after that and works days 5, 6, 1 and 2.
Every day has exactly two crews on, so the pattern fits two posts, like a day team and an evening team.
How many hours does a week hold?
The loop repeats after 6 days, but the calendar week is 7. Over 42 days, a person works 28 shifts. In weeks running Monday to Sunday, with the first shift on a Monday, the shift counts are 5, 5, 5, 5, 4 and 4.
| Shift length | 5 shift week | 4 shift week | Average week |
|---|---|---|---|
| 8 hours | 40 | 32 | 37.3 |
| 10 hours | 50 | 40 | 46.7 |
| 12 hours | 60 | 48 | 56 |
Shifts in 42 days: 7 loops x 4 = 28
Average shifts a week: 28 / 6 = 4.67
8 hour shifts: 4.67 x 8 = 37.3 hours
12 hour shifts: 4.67 x 12 = 56 hours
Where does overtime show up?
The U.S. Department of Labor says overtime is counted for hours over 40 in each workweek, with no averaging over two or more weeks. With 8 hour shifts the five shift weeks reach exactly 40 and stop there. With 10 or 12 hour shifts, the five shift weeks go over by 10 or 20 hours, and the four shift weeks go over by 0 or 8.
A 6 day loop and a 7 day payroll week drift apart. Check the grid against the payroll week every time you post it.
What do you hand out?
- Choose the first day for Crew A and count four days on.
- Start Crew B two days after Crew A, and Crew C two days after Crew B.
- Write the shift start and end hours at the top.
- Print a 6 week sheet so each person sees how the days shift against the calendar.
Print the week by role with your events and a QR code. Printing also posts it to your team.
What are the neighboring patterns?
If you prefer a longer break, look at the 4 on 4 off schedule. If you want the same four days of work in a plain week, read about the 4-10 work schedule.
FAQ
How long is the 4 on 2 off cycle?
Six days: four on and two off.
How many crews does 4 on 2 off need?
Three crews cover two posts. Each day has two crews working.
How many shifts a week is 4 on 2 off?
4.67 on average, or 28 shifts every 42 days.
Is overtime owed on 4 on 2 off?
It depends on shift length. With 8 hour shifts, no week goes over 40. With longer shifts, overtime shows up in the five shift weeks.
Sources
Related guides
- 4 On 4 Off Schedule: How the 8 Day Cycle Works
- How Does a 4/10 Work Schedule Work? Four 10-Hour Days
- 4 On 3 Off Schedule: How the 7 Day Pattern Works
- 48-96 Schedule: Two Days On, Four Days Off
- 12-Hour Shift Schedules: 2-2-3, DuPont and 4 on 4 off
Try ShiftGarden to put your week on one page.